UTILIZING SITE CHARACTERISTICS IN NEURAL NETWORK MODELLING OF PERCENTAGE COST-TIME OVERRUN OF BUILDING PROJECTS

Authors

  • A. O. Ujene
  • A. A. Umoh

DOI:

https://doi.org/10.33736/jcest.374.2017

Keywords:

Building Projects, Construction Industry, Cost Overrun, Site Characteristics, Time Overrun

Abstract

This study evaluated the site characteristics influencing the time and cost delivery of building projects, determined the range of percentage cost and time overrun and developed a neural network model for predicting the percentage cost and time overrun using the site characteristics of building projects. The study evaluated twelve site characteristics and two performance indicators obtained from records of construction costs, contract documents, and valuation reports of 126 purposively sampled building projects spread across several cities in Nigeria. Analyses were with descriptive and artificial neural network. It was concluded that with fairly favourable site characteristics, cost overrun range reached 77.95% with a mean variation of 44.36%, while time overrun range reached 51.23% with a mean variation of 26.77%. It was found that the accuracy performance levels of 91.93% and 91.43% for the cost and time overrun predictions respectively were very high for the optimum models. Building projects have eight significant site characteristics which can be used to reliably predict the percentage overrun, among which the ground water level, level of available infrastructure and labour proximity around the site are the most important predictors of cost and time overrun. The study recommended that project owners, consultants, contractors and other stakeholders should always use the eight identified site characteristics in predicting percentage cost and time overrun, with more priority on the first three characteristics. The study also recommended the neural network prediction approach due to its prediction accuracy.

References

Ijigah, E.A., Ogunbode, E.B., and Ibrahim, M.O. 2012. ''Analysis and Prediction of Cost and Time Overrun of Millennium Development Goals (MDGS) Construction Projects in Nigeria,'' Developing Country Studies, 2(10): 140-147.

Ujene, A.O. ''Integrating Environmental Priority Concerns in Building Planning and Production in Niger Delta, Nigeria,'' Journal of Architecture, Planning & Construction Management, 4(2): 37-56, 2014.

Ujene, A.O. 2012. ''Dynamics of Direct Costs of Building Elements in South-South, Nigeria. An Unpublished PhD Thesis, Department of Building, University of Uyo, Nigeria,''.

Aliyu, A.A., Kasim, R. and Martin, D. 2011. ''Factors Affecting Housing Development in Makama Jahun Area of Bauchi Metropolis, Nigeria,'' International Journal of Trade, Economics and Finance, 2(4): 263-268.

https://doi.org/10.7763/IJTEF.2011.V2.114

Achuenu, E. and Ujene, A.O. 2006. ''Evaluation of Material and Labour Cost of Building Elements in Nigeria, Nigerian Journal of Construction Technology and Management, 7(1): 99-110.

Ugonabo, C.U. and Emoh, F.I. 2013. ''The Major Challenges to Housing Development and Delivery in Anambra State of Nigeria,'' Civil and Environmental Research, 3(4): 1-19.

. Memon, A. H., Rahman, I. A., Abdullah, M. R and Abdu Azis, A. A. 2010. ''Factors Affecting Construction Cost in Mara Large Construction Project: Perspective of Project Management Consultant,'' International Journal of Sustainable Construction Engineering & Technology, 1(2):41-54.

https://doi.org/10.22452/jscp.vol2no1.4

Amusan, L.M. 2011. ''Study of Factors Affecting Construction Cost Performance in Nigerian Construction Sites,'' Unpublished Article, assessed from: http://eprints. Covenant university. edu.ng/121/1/COST_PERFORMANCE2.doc, date assessed 28/05/2011.

Wakita, O. A and Linde, R. M. 2003. ''The Professional Practice of Architectural Working Drawing,'' (3rd ed.), New York: John Willie & Sons, Inc., pp. 240-260.

Okali, D., Okpara, E and Olawoye, J. 2001. ''Rural-Urban Interactions and Livelihood Strategies a Case of Aba and its Region, Southeastern Nigeria,'' A Working Paper Series on Human Settlements Programme, International Institute for Environment and Development (IIED).

Al- Juwairah, Y.A. 1997. ''Factors Affecting Construction Cost in Saudi Arabia,'' Unpublished Master Thesis, King Fahd University of Petroleum and Minerals. Saudi Arabia. Retrieved from; http://eprints.kfupm.edu.sa/10044/, accessed: 20/ 10/ 2010.

Daramola, S. A., Alagbe, O. A., Aduwo, B. and Ogbiye, S.A. 2005. ''Public-Private Partnership and Housing Delivery in Nigeria,'' Proceedings of African Union of Architects Congress, Abuja, Nigeria. 23 - 28, May.

Alagbe, A. O. 2010. ''Knowledge as a Determinant of Acceptability of Compressed Stabilized Laterite Bricks for Affordable Housing in Nigeria,'' Paper presented at XXXVII IAHS World Congress on Housing, October 26 - 29, Santander, Spain.

UOFPP, 2003. ''Site Selection Process,'' A Report Prepared by the University Office for Facilities Planning and Programs, University of Illinois, Urbana-Champaign.

Li, H., Yu, L and Cheng, E. W. L. 2005. ''A GIS‐Based Site Selection System for Real Estate Projects,'' Construction Innovation, 5(4): 231 - 241.

https://doi.org/10.1108/14714170510815276

Monoliadis, O. G., Pantouvakis, J. P. and Tsolas, I. E. 2008. ''Compromise Programming Model in Site Selection for Construction Temporary Facilities, International Journal of Operation Research, 7 (3): 381-400.

https://doi.org/10.1007/BF03024854

Omole, F. K., and Owoeye, J.O. 2012. ''Impact of Rocky Topography on Settlement Pattern and Housing Development in Idanre, Nigeria," Mediterranean Journal of Social Sciences, 3 (3): 517-527.

Oduwaye, L. 2009. ''Spatial Variations of Values of Residential Land Use in Lagos Metropolis,'' An International Multi-Disciplinary Journal, Ethiopia, 3(2): 381-403.

https://doi.org/10.4314/afrrev.v3i2.43638

Ogunsemi, D. R., and Aje, I. O. 2006. ''A Model for Contractors' Selection in Nigeria,'' Journal of Financial Management of Property and Construction, 11(1): 33-44.

https://doi.org/10.1108/13664380680001078

Takim, R. and Akintoye, A. 2002. ''Performance Indicators for Successful Construction Project Performance,'' In: Greenwood, D (Ed.), 18th Annual ARCOM Conference, 2-4 September, University of Northumbria. Association of Researchers in Construction Management, 2: 545-555.

Fagbenle, O. I., and Oluwunmi, A. O. 2010. ''Building Failure and Collapse in Nigeria: The Influence of the Informal Sector,'' Journal of Sustainable Development, 3(4): 268-278.

https://doi.org/10.5539/jsd.v3n4p268

Adindu, C. C. and. Ibironke, O. T. 2012. ''Effect of Construction Risks and Uncertainties on Time and Cost Strategies of Building Contracts in Nigeria,'' Journal of Environmental Management and Safety, 3(2): 105 -117.

Love, P. E. D., Wang, X., Sing, C. and Tiong, R. L. K. 2013. ''Determining the Probability of Project Cost Overruns'' Journal of Construction Engineering and Management, 139 (3): 321-330.

https://doi.org/10.1061/(ASCE)CO.1943-7862.0000575

Chukwu, S. C. and Nwachukwu, A. N. 2012. ''Analysis of Some Meteorological Parameters Using Artificial Neural Network Method for Makurdi, Nigeria,'' African Journal of Environmental Science and Technology, 6(3):182-188.

https://doi.org/10.5897/AJEST11.350

Jamous, H. A. 2013. ''Parametric Cost Estimation of Road Projects Using Artificial Neural Networks,'' An M.Sc Thesis submitted to The Islamic University - Gaza Deanery of Graduate Studies Faculty of Engineering Civil Engineering Department Construction Management.

Dainty, A. R. J. 2008. ''Methodological Pluralism in Construction Management Research,'' In: Knight, A. and Ruddock, L. eds. Advanced Research Methods in the Built Environment. Oxford: Wiley-Blackwell. Pp.1-11.

Fletcher, L. 2002. ''Statistical Modeling by Neural Networks,'' A PhD thesis in Statistics, University of South Africa, South Africa.

Doreswamy, H. and Vastrad, C. M 2013. ''Performance Analysis of Neural Network Models for Oxazolines and Oxazoles Derivatives Descriptor Dataset,'' International Journal of Information Sciences and Techniques (IJIST), 3(6): 1-14.

https://doi.org/10.5121/ijist.2013.3601

Wilmot, C.G. and Mei, B. 2005. ''Neural Network Modeling of Highway Construction Costs,'' Journal of Construction Engineering and Management, 131(7):765-771.

https://doi.org/10.1061/(ASCE)0733-9364(2005)131:7(765)

Alhassan, M., Adejumo, T. W. and Boiko, I. L. 2012. ''Classification of Subsoil Bases in Nigeria,'' The Electronic Journal of Geotechnical Engineering, 17: 1407- 1413.

Aluko, O. 2011. ''Development Control in Lagos State: An Assessment of Public Compliance to Space Standards for Urban Development,'' International Multidisciplinary Journal, Ethiopia, 5 (5): 169-184.

https://doi.org/10.4314/afrrev.v5i5.14

Oisasoje, O. M. and Aidelunuoghene, O. S. 2012. ''The Role of Public Infrastructure in Poverty Reduction in the Rural Areas of Edo State, Nigeria,'' Research on Humanities and Social Sciences, 2(7): 109-120.

Edet, A., Nganje, T. N., Ukpong, A. J. and Ekwere, A. S. 2011. ''Groundwater Chemistry and Quality of Nigeria: A status review'' African Journal of Environmental Science and Technology, 5(13): 1152-1169.

https://doi.org/10.5897/AJESTX11.009

Ikejiofor, U.C. 2009. ''Planning within a Context of Informality: Issues and Trends in Land Delivery, Enugu, Nigeria. Case study prepared for Revisiting Urban Planning: Global Report on Human Settlements,'' Available: http://www.unhabitat.org/grhs/2009, accessed on 15/5/2015.

Oladapo, A.A. 2007. ''A quantitative assessment of the cost and time impact of variation orders on construction projects,'' Journal of Engineering, Design and Technology, 5(1), 35 - 48.

https://doi.org/10.1108/17260530710746597

ElSawy, I., Hosny, H. and. Razek, M. A. 2011. ''A Neural Network Model for Construction Projects Site Overhead Cost Estimating in Egypt,'' International Journal of Computer Science Issues, 8 (3): 273-283.

Gunaydın, H. M. and Dogan, S. Z. 2004. ''A Neural Network Approach for Early Cost Estimation of Structural Systems of Buildings,'' International Journal of Project Management, 22: 595-602.

https://doi.org/10.1016/j.ijproman.2004.04.002

Abujamous, H. K., Rustom, R. N. and Abukmail, M. Y. 2014. ''Influencing Cost Factors in Road Projects in Gaza Strip Using Artificial Neural Network,'' Journal of Engineering Research and Technology, 1(4): 24-33.

Kitikidou, K. and Iliadis, L. 2012. ''Developing Neural Networks to Investigate Relationships Between Air Quality and Quality of Life Indicators,'' In: Air Pollution - Monitoring, Modelling and Health, Khare, M. (Ed.), Rijeka, Croatia: InTech. Available from: http://www.intechopen.com/books/air-pollutionmonitoring-modelling-and-health/ developing -neural-networks-to-investigate-relationships-between-air-qualityand-quality-of-life-indi.

https://doi.org/10.5772/34609

Downloads

Published

2017-05-04

How to Cite

Ujene, A. O., & Umoh, A. A. (2017). UTILIZING SITE CHARACTERISTICS IN NEURAL NETWORK MODELLING OF PERCENTAGE COST-TIME OVERRUN OF BUILDING PROJECTS. Journal of Civil Engineering, Science and Technology, 8(1), 1–15. https://doi.org/10.33736/jcest.374.2017