BLUEPRINT TO BREAKDOWN: FACTORS AND IMPACTS OF EARLY CONTRACTOR TERMINATION IN MALAYSIAN HOUSING PROJECTS
DOI:
https://doi.org/10.33736/jcest.8996.2026Keywords:
early termination, housing, main contractor, factor, impactAbstract
Malaysia, as a fast-developing nation, is experiencing a serious shortage of housing, surpassing the government’s capacity to meet citizens’ needs due to rapid population and urban growth. Despite efforts to meet this demand, the early termination of main contractors in housing projects continues to affect the industry, causing consequences such as project delays and cost overruns. This paper reports research that aims (1) to identify the key factors leading to the early termination of main contractors in Malaysian housing projects, and (2) to investigate the resulting impacts. A qualitative approach was adopted, using semi-structured interviews with five respondents from the developer, main contractor, and consultant perspectives. The study identified four key factor categories—client-related, consultant-related, contractor-related, and external—and four impact categories—operational, stakeholder, economic, and psychological/team dynamics. The findings will assist the Ministry of Housing and Local Government (KPKT) in understanding these factors and impacts, enabling the development of mitigation measures and initiatives to improve housing delivery in line with the National Housing Policy 2018–2025.
References
Muhammad, Z., & Johar, F. (2019). Critical success factors of public–private partnership projects: a comparative analysis of the housing sector between Malaysia and Nigeria. International Journal of Construction Management, 19(3), 257–269. https://doi.org/10.1080/15623599.2017.1423163
Department of Statistics Malaysia (DOSM). (2016, November). Population Projection (Revised), Malaysia, 2010-2040. Retrieved from https://www.dosm.gov.my/portal-main/release-content/population-projection-revised-malaysia-2010-2040
Tumi, S. A. H., Omran, A., & Pakir, A. H. K. (2009). Causes of delay in construction industry in Libya. The International Conference on Economics and Administration. Retrieved from http://conference.faa.ro
Nasir, A. N. M. (2023). KPKT berjaya pulihkan 50 projek perumahan swasta sakit dan terbengkalai bagi bulan Oktober 2023. Retrieved from https://dmedia.penerangan.gov.my/upload/sm/01122023.981240186.pdf
Riveros, C., Ruiz, A. L., Mesa, H. A., & Guevara, J. A. (2022). Critical factors influencing early contract termination in public design–build projects in developing and emerging economies. Buildings, 12(5). https://doi.org/10.3390/buildings12050614
Adros, N. A., & Abidin, D. N. Z. (2019). An investigation of the diversification roles of contractor. SEISENSE Journal of Management, 2(2), 1–12. https://doi.org/10.33215/sjom.v2i2.93
Anyanwu, C. I. (2013). The role of building construction project team members in building projects delivery. IOSR Journal of Business and Management, 14(1), 30–34. https://doi.org/10.9790/487x-1413034
Havila, V., Medlin, C. J., & Salmi, A. (2013). Project-ending competence in premature project closures. International Journal of Project Management, 31(1), 90–99. https://doi.org/10.1016/j.ijproman.2012.05.001
Toader, C.-S., Brad, I., Adamov, T. C., Marin, D., & Moisa, S. (2010). The main causes which lead to success or failure of a project. In Scientific Papers: Animal Science & Biotechnologies / Lucrari Stiintifice: Zootehnie si Biotehnologii (Vol. 43, pp. 449–453). Retrieved from http://library.gcu.edu:2048/login?url=http://search.ebscohost.com/login.aspx?direct=true&db=a9h&AN=60948199&site=eds-live&scope=site
Akinshipe, O., Aigbavboa, C., Madidimalo, M., & Thwala, W. D. (2019). Premature project closure: The part played by clients. In IOP Conference Series: Materials Science and Engineering (Vol. 640). https://doi.org/10.1088/1757-899X/640/1/012028
Yong, Y. C., & Mustaffa, N. E. (2012). Analysis of factors critical to construction project success in Malaysia. Engineering, Construction and Architectural Management, 19(5), 543–556. https://doi.org/10.1108/09699981211259612
Abeynayake, D. N., & Kumara, R. N. M. U. (2013). Effects of premature termination: Case studies of Sri Lankan construction projects. In The Second World Construction Symposium (pp. 199–207)
Alaghbari, W., Kadir, M. R. A., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192–206. https://doi.org/10.1108/09699980710731308
CIDB Malaysia. (2015). Homewest Sdn Bhd v Vision Returns Sdn Bhd [2016] 1 CIDB-CLR 105. CIDB Construction Law Report 2015, 2015 . ARK, 105–109
CIDB Malaysia. (2016). Target Resources Sdn Bhd v Putrajaya Holdings Sdn Bhd [2017] 1 CIDB-CLR 165. CIDB Construction Law Report 2016, 2016 . ARK, 165–173
CIDB Malaysia. (2017). Sunshine Fleet Sdn Bhd v Jabatan Kerja Raya Malaysia & Anor [2018] 1 CIDB-CLR 193. CIDB Construction Law Report 2017, 2017 . ARK, 193–204
Yong, Y. C., & Mustaffa, N. E. (2017). Critical success factors for Malaysian construction projects: An investigative review. International Journal of Built Environment and Sustainability, 4(2). https://doi.org/10.11113/ijbes.v4.n2.180
Iyiola, K., & Rjoub, H. (2020). Using conflict management in improving owners and contractors relationship quality in the construction industry: The mediation role of trust. SAGE Open, 10(1). https://doi.org/10.1177/2158244019898834
Jelodar, M. B., Yiu, T. W., & Wilkinson, S. (2015). Systematic representation of relationship quality in conflict and dispute: For construction projects. Construction Economics and Building, 15(1), 89–103. https://doi.org/10.5130/ajceb.v15i1.4281
Wu, G., Liu, C., Zhao, X., & Zuo, J. (2017). Investigating the relationship between communication-conflict interaction and project success among construction project teams. International Journal of Project Management, 35(8), 1466–1482. https://doi.org/10.1016/j.ijproman.2017.08.006
Akinshipe, O., Aigbavboa, C., Thwala, W. D., & Madidimalo, M. (2019). Premature project closure: the role of consultants and contractors. https://doi.org/10.33796/waberconference2019.58
Abdul Kadir, M. R., Lee, W. P., Jaafar, M. S., Sapuan, S. M., & Ali, A. A. A. (2005). Factors affecting construction labour productivity for Malaysian residential projects. Structural Survey, 23(1), 42–54. https://doi.org/10.1108/02630800510586907
Zainon, A., Ayob, A., Arkam, M., Munaaim, C., Faiz, M., Zaki, M., & Elyas, S. F. (2016). Bid evaluation strategy among G7 construction companies in northern states of Malaysia. Research Journal Of Fisheries And Hydrobiology, 11(3), 24–30. Retrieved from http://www.aensiweb.com/JASA/http://creativecommons.org/licenses/by/4.0/
Lode, D., Lee, J. C., Yusof, Z. M., & Lee, S. (2023). Employment of foreign workers at construction industry in Malaysia—A review. Lecture Notes in Civil Engineering, 310, 213–222. https://doi.org/10.1007/978-981-19-8024-4_18
Abdul-Aziz, A. R. (2001). Foreign workers and labour segmentation in Malaysia’s construction industry. Construction Management and Economics, 19(8), 789–798. https://doi.org/10.1080/01446190110072022
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007
Gabula, Z. H. (2012). Factors influencing the construction project success rates of Reconstruction Development Programme ( RDP ) housing projects in the Eastern Cape : A quality perspective : A census study. Durban University of Technology.
El-Rayes, K., & Moselhi, O. (2001). Optimizing resource utilization for repetitive construction projects. Journal of Construction Engineering and Management, 127(1), 18–27. https://doi.org/10.1061/(asce)0733-9364(2001)127:1(18)
Adu-Gyamfi, A., Poku-Boansi, M., Darpoh, L., Asibey, M. O., & Owusu-Ansah, J. K. (2023). Rainfall challenges and strategies to improve housing construction in Sub-Saharan Africa: The case of Ghana. Housing Studies, 38(7), 1155–1190. https://doi.org/10.1080/02673037.2021.2014412
Akinshipe, O., Aigbavboa, C., Thwala, W. D., & Mutshaeni, M. (2021). External components of premature construction project closure. In Advances in Science, Technology and Innovation (pp. 285–288). Springer. https://doi.org/10.1007/978-3-030-48465-1_47
Alao, O. O., & Jagboro, G. O. (2017). Assessment of causative factors for project abandonment in Nigerian public tertiary educational institutions. International Journal of Building Pathology and Adaptation, 35(1), 41–62. https://doi.org/10.1108/IJBPA-07-2016-0016
Elijah Olusegun, A., & Olumuyiwa Michael, A. (2011). Abandonment of construction projects in Nigeria: Causes and effects. Journal of Emerging Trends in Economics and Management Sciences, 2(2), 2141–7024. Retrieved from http://jetems.scholarlinkresearch.com/articles/Abandonment of Construction Projects in Nigeria.pdf
Ihuah, P. W., & Benebo, A. M. (2014). An assessment of the causes and effects of abandonment of development projects on real property values in Nigeria, 2, 25–36. Retrieved from https://www.researchgate.net/publication/265793952
Khahro, S. H., Memon, A. H., Memon, N. A., Memon, Z. A., & Naresh, R. (2023). Influence of social and economic factors on construction project performance in Pakistan. Sustainability (Switzerland), 15(3). https://doi.org/10.3390/su15032469
Nistorescu, T., & Ploscaru, C. (2010). Impact of economic and financial crisis in the construction industry. Management and Marketing Journal. University of Craiova]. www.fiec.com. Retrieved from http://ideas.repec.org/a/aio/manmar/vviiiy2010i1p25-36.html
Aziz, A. (2023). SIAB, Yong Tai mutually terminate two outstanding condominium projects valued at RM190.4 mil. The Edge Malaysia. Retrieved from https://theedgemalaysia.com/node/661704
Salim, S. (2023). TCS mutually terminates construction contract to build condo in Kuala Langat due to higher building material cost. The Edge Malaysia. Retrieved from https://theedgemalaysia.com/node/671913
Madidimalo, M. (2017). Premature project closure in construction projects: A case study of South Africa. University of Johannesburg.
Naderifar, M., Goli, H., & Ghaljaie, F. (2017). Snowball sampling: A purposeful method of sampling in qualitative research. Strides in Development of Medical Education, 14(3). https://doi.org/10.5812/sdme.67670
Yap, J. B. H., Abdul-Rahman, H., & Wang, C. (2018). Preventive mitigation of overruns with project communication management and continuous learning: PLS-SEM approach. Journal of Construction Engineering and Management, 144(5). https://doi.org/10.1061/(asce)co.1943-7862.0001456
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 UNIMAS Publisher

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
During the manuscript submission process, the corresponding author, on behalf of all authors, will be asked to agree to the terms of the Open Access Publishing Agreement by checking the designated agreement box (see Copyright & Licensing for more information).
Open Access Publishing Agreement
1) By agreeing to these terms, the author(s) retain full copyright and grant UNIMAS Publisher the right of first publication. The author(s) also grant UNIMAS Publisher permission to reproduce, recreate, translate, extract, or summarize, and to distribute and display in any forms, formats, and media. The author(s) can reuse their papers in their future printed work without first requiring permission from UNIMAS Publisher, provided that the author(s) acknowledge and refer to the publication in the Journal.
2) The author(s) agree that their articles published under UNIMAS Publisher are distributed under the terms of the Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License (CC BY-NC-SA 4.0), which permits unrestricted use, distribution, and reproduction in any medium, for non-commercial purposes, provided the original work of the author(s) is properly cited.
3) The author(s) are responsible for ensuring their submitted work is original and does not infringe any existing copyright, trademark, patent, statutory right, or proprietary right of others. The corresponding author has obtained permission from all co-authors prior to submission to the journal. Upon submission of the manuscript, the author(s) agree that no similar work has been or will be submitted or published elsewhere in any language. If the submitted manuscript includes materials from others, the authors have obtained permission from the copyright owners.
4) By agreeing to this statement, the author(s) declare that the research which they have conducted complies with the current laws of the respective country and UNIMAS Journal Publication Ethics Policy. Any experimentation or research involving humans or the use of animal samples must obtain approval from the Human or Animal Ethics Committee in their respective institutions. The author(s) agree and understand that UNIMAS Publisher is not responsible for any compensational claims or failure caused by the author(s) in fulfilling the above-mentioned requirements. The author(s) must accept the responsibility for releasing their materials upon request by the Chief Editor or UNIMAS Publisher.
5) The author(s) should have participated sufficiently in the work and ensured the appropriateness of the content of the article. The author(s) should also agree that they have no commercial attachments (e.g., patent or license arrangement, equity interest, consultancies, etc.) that might pose any conflict of interest with the submitted manuscript. The author(s) also agree to make any relevant materials and data available upon request by the editor(s) or UNIMAS Publisher.