BLUEPRINT TO BREAKDOWN: FACTORS AND IMPACTS OF EARLY CONTRACTOR TERMINATION IN MALAYSIAN HOUSING PROJECTS

Authors

  • Yong Cheng Ling School of Housing, Building and Planning, Universiti Sains Malaysia, 11800, USM Penang, Malaysia
  • Nur Syaimasyaza Mansor School of Housing, Building and Planning, Universiti Sains Malaysia, 11800, USM Penang, Malaysia
  • Zairra Mat Jusoh School of Architecture and Built Environment, UCSI University, 56000, Kuala Lumpur, Malaysia

DOI:

https://doi.org/10.33736/jcest.8996.2026

Keywords:

early termination, housing, main contractor, factor, impact

Abstract

Malaysia, as a fast-developing nation, is experiencing a serious shortage of housing, surpassing the government’s capacity to meet citizens’ needs due to rapid population and urban growth. Despite efforts to meet this demand, the early termination of main contractors in housing projects continues to affect the industry, causing consequences such as project delays and cost overruns. This paper reports research that aims (1) to identify the key factors leading to the early termination of main contractors in Malaysian housing projects, and (2) to investigate the resulting impacts. A qualitative approach was adopted, using semi-structured interviews with five respondents from the developer, main contractor, and consultant perspectives. The study identified four key factor categories—client-related, consultant-related, contractor-related, and external—and four impact categories—operational, stakeholder, economic, and psychological/team dynamics. The findings will assist the Ministry of Housing and Local Government (KPKT) in understanding these factors and impacts, enabling the development of mitigation measures and initiatives to improve housing delivery in line with the National Housing Policy 2018–2025.

References

Muhammad, Z., & Johar, F. (2019). Critical success factors of public–private partnership projects: a comparative analysis of the housing sector between Malaysia and Nigeria. International Journal of Construction Management, 19(3), 257–269. https://doi.org/10.1080/15623599.2017.1423163

Department of Statistics Malaysia (DOSM). (2016, November). Population Projection (Revised), Malaysia, 2010-2040. Retrieved from https://www.dosm.gov.my/portal-main/release-content/population-projection-revised-malaysia-2010-2040

Tumi, S. A. H., Omran, A., & Pakir, A. H. K. (2009). Causes of delay in construction industry in Libya. The International Conference on Economics and Administration. Retrieved from http://conference.faa.ro

Nasir, A. N. M. (2023). KPKT berjaya pulihkan 50 projek perumahan swasta sakit dan terbengkalai bagi bulan Oktober 2023. Retrieved from https://dmedia.penerangan.gov.my/upload/sm/01122023.981240186.pdf

Riveros, C., Ruiz, A. L., Mesa, H. A., & Guevara, J. A. (2022). Critical factors influencing early contract termination in public design–build projects in developing and emerging economies. Buildings, 12(5). https://doi.org/10.3390/buildings12050614

Adros, N. A., & Abidin, D. N. Z. (2019). An investigation of the diversification roles of contractor. SEISENSE Journal of Management, 2(2), 1–12. https://doi.org/10.33215/sjom.v2i2.93

Anyanwu, C. I. (2013). The role of building construction project team members in building projects delivery. IOSR Journal of Business and Management, 14(1), 30–34. https://doi.org/10.9790/487x-1413034

Havila, V., Medlin, C. J., & Salmi, A. (2013). Project-ending competence in premature project closures. International Journal of Project Management, 31(1), 90–99. https://doi.org/10.1016/j.ijproman.2012.05.001

Toader, C.-S., Brad, I., Adamov, T. C., Marin, D., & Moisa, S. (2010). The main causes which lead to success or failure of a project. In Scientific Papers: Animal Science & Biotechnologies / Lucrari Stiintifice: Zootehnie si Biotehnologii (Vol. 43, pp. 449–453). Retrieved from http://library.gcu.edu:2048/login?url=http://search.ebscohost.com/login.aspx?direct=true&db=a9h&AN=60948199&site=eds-live&scope=site

Akinshipe, O., Aigbavboa, C., Madidimalo, M., & Thwala, W. D. (2019). Premature project closure: The part played by clients. In IOP Conference Series: Materials Science and Engineering (Vol. 640). https://doi.org/10.1088/1757-899X/640/1/012028

Yong, Y. C., & Mustaffa, N. E. (2012). Analysis of factors critical to construction project success in Malaysia. Engineering, Construction and Architectural Management, 19(5), 543–556. https://doi.org/10.1108/09699981211259612

Abeynayake, D. N., & Kumara, R. N. M. U. (2013). Effects of premature termination: Case studies of Sri Lankan construction projects. In The Second World Construction Symposium (pp. 199–207)

Alaghbari, W., Kadir, M. R. A., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192–206. https://doi.org/10.1108/09699980710731308

CIDB Malaysia. (2015). Homewest Sdn Bhd v Vision Returns Sdn Bhd [2016] 1 CIDB-CLR 105. CIDB Construction Law Report 2015, 2015 . ARK, 105–109

CIDB Malaysia. (2016). Target Resources Sdn Bhd v Putrajaya Holdings Sdn Bhd [2017] 1 CIDB-CLR 165. CIDB Construction Law Report 2016, 2016 . ARK, 165–173

CIDB Malaysia. (2017). Sunshine Fleet Sdn Bhd v Jabatan Kerja Raya Malaysia & Anor [2018] 1 CIDB-CLR 193. CIDB Construction Law Report 2017, 2017 . ARK, 193–204

Yong, Y. C., & Mustaffa, N. E. (2017). Critical success factors for Malaysian construction projects: An investigative review. International Journal of Built Environment and Sustainability, 4(2). https://doi.org/10.11113/ijbes.v4.n2.180

Iyiola, K., & Rjoub, H. (2020). Using conflict management in improving owners and contractors relationship quality in the construction industry: The mediation role of trust. SAGE Open, 10(1). https://doi.org/10.1177/2158244019898834

Jelodar, M. B., Yiu, T. W., & Wilkinson, S. (2015). Systematic representation of relationship quality in conflict and dispute: For construction projects. Construction Economics and Building, 15(1), 89–103. https://doi.org/10.5130/ajceb.v15i1.4281

Wu, G., Liu, C., Zhao, X., & Zuo, J. (2017). Investigating the relationship between communication-conflict interaction and project success among construction project teams. International Journal of Project Management, 35(8), 1466–1482. https://doi.org/10.1016/j.ijproman.2017.08.006

Akinshipe, O., Aigbavboa, C., Thwala, W. D., & Madidimalo, M. (2019). Premature project closure: the role of consultants and contractors. https://doi.org/10.33796/waberconference2019.58

Abdul Kadir, M. R., Lee, W. P., Jaafar, M. S., Sapuan, S. M., & Ali, A. A. A. (2005). Factors affecting construction labour productivity for Malaysian residential projects. Structural Survey, 23(1), 42–54. https://doi.org/10.1108/02630800510586907

Zainon, A., Ayob, A., Arkam, M., Munaaim, C., Faiz, M., Zaki, M., & Elyas, S. F. (2016). Bid evaluation strategy among G7 construction companies in northern states of Malaysia. Research Journal Of Fisheries And Hydrobiology, 11(3), 24–30. Retrieved from http://www.aensiweb.com/JASA/http://creativecommons.org/licenses/by/4.0/

Lode, D., Lee, J. C., Yusof, Z. M., & Lee, S. (2023). Employment of foreign workers at construction industry in Malaysia—A review. Lecture Notes in Civil Engineering, 310, 213–222. https://doi.org/10.1007/978-981-19-8024-4_18

Abdul-Aziz, A. R. (2001). Foreign workers and labour segmentation in Malaysia’s construction industry. Construction Management and Economics, 19(8), 789–798. https://doi.org/10.1080/01446190110072022

Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007

Gabula, Z. H. (2012). Factors influencing the construction project success rates of Reconstruction Development Programme ( RDP ) housing projects in the Eastern Cape : A quality perspective : A census study. Durban University of Technology.

El-Rayes, K., & Moselhi, O. (2001). Optimizing resource utilization for repetitive construction projects. Journal of Construction Engineering and Management, 127(1), 18–27. https://doi.org/10.1061/(asce)0733-9364(2001)127:1(18)

Adu-Gyamfi, A., Poku-Boansi, M., Darpoh, L., Asibey, M. O., & Owusu-Ansah, J. K. (2023). Rainfall challenges and strategies to improve housing construction in Sub-Saharan Africa: The case of Ghana. Housing Studies, 38(7), 1155–1190. https://doi.org/10.1080/02673037.2021.2014412

Akinshipe, O., Aigbavboa, C., Thwala, W. D., & Mutshaeni, M. (2021). External components of premature construction project closure. In Advances in Science, Technology and Innovation (pp. 285–288). Springer. https://doi.org/10.1007/978-3-030-48465-1_47

Alao, O. O., & Jagboro, G. O. (2017). Assessment of causative factors for project abandonment in Nigerian public tertiary educational institutions. International Journal of Building Pathology and Adaptation, 35(1), 41–62. https://doi.org/10.1108/IJBPA-07-2016-0016

Elijah Olusegun, A., & Olumuyiwa Michael, A. (2011). Abandonment of construction projects in Nigeria: Causes and effects. Journal of Emerging Trends in Economics and Management Sciences, 2(2), 2141–7024. Retrieved from http://jetems.scholarlinkresearch.com/articles/Abandonment of Construction Projects in Nigeria.pdf

Ihuah, P. W., & Benebo, A. M. (2014). An assessment of the causes and effects of abandonment of development projects on real property values in Nigeria, 2, 25–36. Retrieved from https://www.researchgate.net/publication/265793952

Khahro, S. H., Memon, A. H., Memon, N. A., Memon, Z. A., & Naresh, R. (2023). Influence of social and economic factors on construction project performance in Pakistan. Sustainability (Switzerland), 15(3). https://doi.org/10.3390/su15032469

Nistorescu, T., & Ploscaru, C. (2010). Impact of economic and financial crisis in the construction industry. Management and Marketing Journal. University of Craiova]. www.fiec.com. Retrieved from http://ideas.repec.org/a/aio/manmar/vviiiy2010i1p25-36.html

Aziz, A. (2023). SIAB, Yong Tai mutually terminate two outstanding condominium projects valued at RM190.4 mil. The Edge Malaysia. Retrieved from https://theedgemalaysia.com/node/661704

Salim, S. (2023). TCS mutually terminates construction contract to build condo in Kuala Langat due to higher building material cost. The Edge Malaysia. Retrieved from https://theedgemalaysia.com/node/671913

Madidimalo, M. (2017). Premature project closure in construction projects: A case study of South Africa. University of Johannesburg.

Naderifar, M., Goli, H., & Ghaljaie, F. (2017). Snowball sampling: A purposeful method of sampling in qualitative research. Strides in Development of Medical Education, 14(3). https://doi.org/10.5812/sdme.67670

Yap, J. B. H., Abdul-Rahman, H., & Wang, C. (2018). Preventive mitigation of overruns with project communication management and continuous learning: PLS-SEM approach. Journal of Construction Engineering and Management, 144(5). https://doi.org/10.1061/(asce)co.1943-7862.0001456

Downloads

Published

2026-09-30

How to Cite

Ling, Y. C., Mansor, N. S., & Jusoh, Z. M. . (2026). BLUEPRINT TO BREAKDOWN: FACTORS AND IMPACTS OF EARLY CONTRACTOR TERMINATION IN MALAYSIAN HOUSING PROJECTS. Journal of Civil Engineering, Science and Technology, 17(2), 152–167. https://doi.org/10.33736/jcest.8996.2026