Analysis of Delay In Execution of Construction Projects
DOI:
https://doi.org/10.33736/jcest.880.2018Abstract
The construction industry is one of the major sectors that provide important ingredients for the development of country’s economy. A survey is conducted to identify the major causes of construction delays, its effects, and minimizing delays in construction projects using relative importance index method. The questionnaire was circulated among various construction companies located in India to find the reasons which are affecting the construction projects in India. The various factors are identified for this purpose and these critical factors are then categorized into owner, contractor, consultant, material, design, labor, equipment and external factors. About fifty six responses are received for the analysis purpose. SPSS software is applied to perform the analysis. The survey is concentrated on the frequency of occurrence of this factors and what is the severity of this factors in the five point scale.
References
Arditi, D., and Robinson, M. A, 1999 Concurrent Delays in Construction Litigation. Journal of Cost Engineering, 37(7), 20-30
Al-Momani, A.H, 2000., Construction delay: A quantitative analysis. International Journal of Project Management, 18(1), 51-59.
https://doi.org/10.1016/S0263-7863(98)00060-X
Sambasivan M and Soon Y, 2007., Causes and effects of delays in Malaysian construction industry, International Journal of Project Management, 25 (5), 517-526.
https://doi.org/10.1016/j.ijproman.2006.11.007
Alkass S, Mazerolle M., and Harris F, 2010.,Construction delay analysis techniques. Journal of Construction Management and Economics, 14(5)., 375-394,.
https://doi.org/10.1080/014461996373250
Aradhana Rathod et al.2013., Delays In Residential Building Construction, International Journal of innovative Research and Development(IJIRD), 2(5).,ISSN NO 2278-0211.
Siddesh K Pai, J.Raj Bharath, 2013.,Analysis Of Critical Causes Of Delays In Indian Infrastructure Projects, International Journal of Innovative Research And Development ISSN: 2278 - 0211. 2(3).,251-263.
B.P. Sunjka and U. Jacob, Significant Causes and Effects of Project Delays in the Niger delta region, Nigeria, Saiie25 Proceedings, 9th - 11th of July 2013, Stellenbosch, South Africa,.
Dr. A. W. Dhawale1, S.C.,2014., Tandale, Analysis of Critical Factors Affecting The Construction Projects in Pune Region, India. International Journal of Civil Engineering and Technology. 5(3), 209-216,.
Prakash Rao, B. and *Joseph Camron Culas, 2014., Causes of Delays in Construction Projects - A Case Study. International Journal of Current Research 6(6), 7219-7222.
T. Subramani , P S Sruthi , M.Kavitha, 2014.,Causes of Cost Overrun In Construction, IOSR Journal of Engineering (IOSRJEN) 4(6)., 1-7.
https://doi.org/10.9790/3021-04640107
Hassan Emam1, Peter Farrell and Mohamed Abdelaal, ,Causes of Delay on Infrastructure Projects in Qatar, University of Bolton, Bolton, Proceedings of 31st Annual ARCOM Conference, 7-9 September 2015, Lincoln, UK, Association of Researchers in Construction Management, 773-782.
Divya.R, S.Ramya, Causes, Effects and Minimization of Delays in Construction Projects, National Conference on Research Advances in Communication, Computation, Electrical Science and Structures (NCRACCESS- 2015)., ISSN NO 2348-8352., 47-53
Asish Ram, Dr. Pratheeba Paul, 2015., Study on Construction Sequence Delay for Road Infrastructure Projects, IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), 12(2) Ver. VI, 15-21, .
Yogita Honrao , Prof.D.B.Desai, 2015.,Study of Delay in Execution of Infrastructure Projects -Highway Construction, International Journal of Scientific and Research Publications, ISSN 2250- 3153, 5(6).,1-8.
Salim S. Mulla, Ashish P. Waghmare, (2015) A Study of Factors Caused for Time & Cost Overruns in Construction Project & their Remedial Measures, Int. Journal of Engineering Research and Applications, ISSN : 2248-9622, 5(1), ( Part -6), .48-53.
Dinesh Kumar R ,2016., Causes and Effects of Delays in Indian Construction Projects, International Research Journal of Engineering and Technology , e-ISSN: 2395 -0056 ., 3(4)., 1831-1837.
Kartik Kalkani Shakil Malek, 2016., Analysing Causes of Delay in Construction Projects, International Journal for Innovative Research in Science & Technology, ISSN NO 2349-6010, 2(12),.257-262.
TsegayGebrehiwet.,HanbinLuo., 2017., Analysis of delay impact on construct project based on RII and Correlation coefficient: Empirical study., Vol.196., 366-374.
https://doi.org/10.1016/j.proeng.2017.07.212
Desalegn Disasa Daba, Dr. Jayeshkumar Pitroda .,2018, A Critical Literature Review on Main Cause of Delay in Construction Projects International Journal for Innovative Research in Science & Technology, ISSN NO 2395- 0056, 5(1), 612-615.
Downloads
Published
How to Cite
Issue
Section
License
During the manuscript submission process, the corresponding author, on behalf of all authors, will be asked to agree to the terms of the Open Access Publishing Agreement by checking the designated agreement box (see Copyright & Licensing for more information).
Open Access Publishing Agreement
1) By agreeing to these terms, the author(s) retain full copyright and grant UNIMAS Publisher the right of first publication. The author(s) also grant UNIMAS Publisher permission to reproduce, recreate, translate, extract, or summarize, and to distribute and display in any forms, formats, and media. The author(s) can reuse their papers in their future printed work without first requiring permission from UNIMAS Publisher, provided that the author(s) acknowledge and refer to the publication in the Journal.
2) The author(s) agree that their articles published under UNIMAS Publisher are distributed under the terms of the Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License (CC BY-NC-SA 4.0), which permits unrestricted use, distribution, and reproduction in any medium, for non-commercial purposes, provided the original work of the author(s) is properly cited.
3) The author(s) are responsible for ensuring their submitted work is original and does not infringe any existing copyright, trademark, patent, statutory right, or proprietary right of others. The corresponding author has obtained permission from all co-authors prior to submission to the journal. Upon submission of the manuscript, the author(s) agree that no similar work has been or will be submitted or published elsewhere in any language. If the submitted manuscript includes materials from others, the authors have obtained permission from the copyright owners.
4) By agreeing to this statement, the author(s) declare that the research which they have conducted complies with the current laws of the respective country and UNIMAS Journal Publication Ethics Policy. Any experimentation or research involving humans or the use of animal samples must obtain approval from the Human or Animal Ethics Committee in their respective institutions. The author(s) agree and understand that UNIMAS Publisher is not responsible for any compensational claims or failure caused by the author(s) in fulfilling the above-mentioned requirements. The author(s) must accept the responsibility for releasing their materials upon request by the Chief Editor or UNIMAS Publisher.
5) The author(s) should have participated sufficiently in the work and ensured the appropriateness of the content of the article. The author(s) should also agree that they have no commercial attachments (e.g., patent or license arrangement, equity interest, consultancies, etc.) that might pose any conflict of interest with the submitted manuscript. The author(s) also agree to make any relevant materials and data available upon request by the editor(s) or UNIMAS Publisher.